Portbury Project for ISD

Heavy duty vis-queen laid at 300 laps on insulation & setting out Kota Screed rails supplied by Euro Accessories.

Starting to level and set the Peikko movement joint.

Peikko Movement joint bedded in with C40 Newton Concrete.

Kota Screed rails splitting the area into bay sizes & bedded in at correct level with C40 Concrete.

 

A193 mesh cut with flying ends set at 300 laps and on 75mm line spacers tied with tie wire using battery operated tie wire guns.

Pipeline of Concrete pump placed into position to enable commencement of pour 1 into bay number 1

Bay 1 laid and sprayed with floor sealer.