Greggs at Cambuslang for P H Insulations Glycol Heater Mat protection Screed

Setting up the pipeline of the concrete pump

Showing the glycol heater mat during our set up process

Start of the pour – C16/20 Newton Concrete mcc 350kgs CEM 1 10mm aggreagte 150 slump pump mix with WRA

800m² at 50mm deep pour completed with a magic screed finish